Gilbane Building
Co.
~ Fidelity Investments (Boston, Mass.)
Phase I
This project consisted of the complete interior demolition and removal
of asbestos containing materials from the office areas and basement mechanical
room in an eleven story office building (60,000sqft. per floor). This
project also included the recycling of 660,000sqft. of Armstrong ceiling
tiles.
Phase II
This phase consisted of the complete demolition of the building core areas
(public restrooms and mechanical rooms and closets at each floor). ACM
Corp. also performed all the core drilling and concrete cutting to facilitate
the installation of new mechanical, electrical and plumbing chases and
constructed the structural infills at the previous locations of these
chases.
|